Isolations and shutdowns: how to plan water shutdowns in occupied buildings

A planned water shutdown should be short, announced and uneventful. Here is how to plan one in an occupied building and restart without surprises.

24/7 PRIORITY RESPONSE | WORK ORDERS | COMPLIANCE PACK

Google

Overall Rating

4.9

Five stars

(3,000+)

Brightest & Best Business Awards: Winner 2019, Winner 2024, Winner 2025, People's Choice 2025, Finalist 2023

NOW SERVICING NORTH SYDNEY

  • NSW Contractor Licence 285594C
  • 24/7 Priority Response
  • 5,183 Commercial Jobs Since 2019
  • Report and Photos on Every Job
  • Invoices With Your PO and SP Number
  • Onsite in 30 Minutes Guaranteed

KEY TAKEAWAYS

Quick answer

Reviewed by William Demirdonder, licensed plumber, NSW licence 275278C, on 8 November 2026

  • Building managers
  • Facility managers
  • Strata managers
  • Planning
  • 6 min read

Quick answer

Shut off the smallest area for the shortest time. Before the day, find and test the valves, list everything that loses water, check your by-laws or leases for notice rules, and give residents or tenants written notice with the times and a contact. On restart, open valves slowly, bleed air, check the hot water plant and outlet temperatures, and look for leaks below the work.

  • Test the isolation valves before the day, not on it.
  • List everything that loses water, including plant and equipment.
  • Never isolate fire services without your fire services contractor.
  • Restart slowly, then check hot water temperatures and look for leaks.

GUIDE

Why shutdowns happen

Most plumbing repairs need the water off: replacing a valve, working on the hot water plant, testing a backflow device or relining a stack. The aim is always the same: shut off the smallest part of the building, for the shortest time, at the least disruptive hour.

GUIDE

Know your valves first

The size of a shutdown depends on the valves. If the floor valve has seized, the plumber has to go back to the riser valve. If that has seized too, the whole building may go off.

  • Keep a valve map showing which valve feeds which floors and lots.
  • Have the valves you will need checked before the day.
  • Replace failed valves as a separate, planned job, so future shutdowns are smaller.

Height adds time. When a riser is isolated, the water already in the pipes above the work has to drain out before the plumber can cut in, and it has to be refilled and bled afterwards. In a tall building that drain-down and refill can take longer than the repair itself, so ask for the whole window, not only the repair time. If the building has booster pumps or pressure reducing valves, the plumber should decide how they are handled during the isolation.

GUIDE

Plan the shutdown

  1. Scope: which floors, lots or tenancies lose water, and whether hot, cold or both.
  2. Timing: avoid morning and evening peaks, and trading hours for businesses.
  3. What else loses water: hot water plant, kitchen and laundry equipment, medical or dental equipment, cooling plant, irrigation and pumps.
  4. Fire services: talk to your fire services contractor before any isolation that could affect them, and let them handle those valves.
  5. Notice: check your by-laws, leases and any notice rules with your strata or property manager, and give as much notice as you can.
  6. People who need extra help: residents with medical needs, and anyone who cannot easily leave the building.
  7. On the day: keys and access confirmed, parts on site, and a contact for questions.

GUIDE

What the notice should say

  • The date, start and finish time, and which areas are affected.
  • What to do beforehand: fill a kettle and some bottles, and turn off taps and appliances.
  • Not to use hot water until it is restored.
  • What to expect afterwards: spluttering taps and some discoloured water for a short time.
  • Who to contact on the day.

A typical notice, to adapt: "Planned water shutdown, Tuesday 12 May, 9am to 1pm, levels 4 to 8, hot and cold water. Please fill a kettle and some bottles beforehand, and check every tap is turned off. Do not use the hot water until 1pm. Taps may splutter and run cloudy for a minute when the water returns. Questions on the day: building manager, phone number." Short, specific and pinned where people actually look, such as the lift and the mailroom.

Watch out

Taps left open during a shutdown can flood a lot when the water comes back on. Remind everyone to check their taps are off.

GUIDE

A typical shutdown, step by step

WhenWhat happens
Two to three weeks beforeScope and time agreed, valves checked, fire services contractor consulted if needed, notice sent
The day beforeReminder notice, parts and access confirmed, anyone with extra needs contacted directly
StartHeating on the hot water plant turned off if its supply will be isolated, then the valves closed and the section drained
WorkThe repair or replacement, with the plumber keeping the building contact updated if the time will run over
RestartSlow refill, air bled, plant restarted, temperatures and leaks checked
AfterAll-clear notice, times recorded, and any valve that misbehaved added to the repair list

This is a generic pattern, not a fixed timetable. A single tap replacement on one floor and a hot water plant changeover are very different jobs.

GUIDE

Shops, offices and mixed-use buildings

In a building with shops or offices, a shutdown during trading hours costs tenants money. Cafés and restaurants cannot open without water, and clinics may need to cancel appointments. Talk to tenants early about the right time, which is usually before opening or after close.

Where a short daytime shutdown cannot be avoided, a temporary supply or doing the work in stages can keep the most sensitive tenants running. Ask the plumber what is possible when you get the quote, not on the day.

GUIDE

Restart without surprises

  • Open valves slowly, to limit water hammer and pressure shocks.
  • Bleed air from the high points, and run taps until the water is clear.
  • Check the hot water plant restarts and circulates properly.
  • Check outlet temperatures at TMVs. In NSW, outlets in aged care, patient care, childcare, school and disability areas must be no hotter than 45°C, and no hotter than 50°C elsewhere (NCC, NSW variation).
  • Look for leaks at the work area and on the floor below.
  • Confirm every affected lot or tenancy has water, then record the times.

Ask your plumber

Could an extra isolation valve make this shutdown, and every future one, smaller?

For planned work on central plant, see hot water plant. A Building Care Plan can also check and exercise your valves before you need them.

QUESTIONS

Questions

SERVICES

How we can help

SOURCES

Sources

Last updated 8 November 2026. General information, not legal advice.

COMMERCIAL & STRATA

Explore Commercial & Strata

KNOWLEDGE CENTRE

Need a hand with this?

Log a job, or start with a free health check of your building.